Many readers expressed frustration at the slow management leading to significant damage to wind power enterprises and asked the question: who is responsible for these damages?
As Thanh Nien reported, the Gia Lai Department of Industry and Trade said that in this province, there are currently 629 MW of wind power that has not been connected for commercial operation despite having completed construction work for many months. The reason is that there is presently no selling price for wind power projects completed after October 31, 2021. Accordingly, the loss of electricity output is about 4.5 billion kWh with a value of about 8,500 billion VND, leading to the loss of local tax revenue and pressure to repay bank loans of investors (investors). higher. Facing the above situation, the Gia Lai Department of Industry and Trade has proposed to the Ministry of Industry and Trade for wind power projects to operate commercially soon and conduct electricity purchases and sales.
Hundreds of strawberries poured into the business
Readers (BD) Thanh Nien said that this delay not only causes thousands of billions of dong in damage, making it difficult for businesses, but also a waste of national electricity. “Delayed and inconsistent policies cause economic damage to businesses and loss of budget for the locality. Who will be responsible for this?", Thanh Binh BD commented. And Tran Thanh BD is urgent: "Hundreds of strawberries poured into enterprises. It's a problem if it's built and then sold or not, and then it's forced to price again."
Gia Lai's wind power potential attracts investors TRẦN HIẾU |
"It is necessary to prosecute the ministries and branches that encourage investors to make wind power, and then which stage is responsible for purchasing electricity without signing power purchase and sale contracts with investors to cause damage and waste like this", BD Le Nghiep raise the problem. Similarly, BD Hong Quan wrote: "Whose responsibility is it in this matter? To waste 8,500 billion is worse than corruption. It is recommended to strictly handle those responsible for the incident.”
“Why don't you connect and transmit to the national source, it's considered a lack of sales, the price will be charged tomorrow? How much is the construction cost, the country is short of electricity, but if there is a loss of thousands of billions like that, there is no one, what's wrong with any department?", urgent Thanh Tung BD.
Need to remove soon
In parallel with the proposal to be held responsible for wasting and losing electricity, BD also suggested that the authorities soon have a direction to "untie" businesses. BD Song Bach wrote: "Wind power is a clean, environmentally friendly energy, making an important contribution to offset the shortage of electricity due to thermal power projects, ensuring national energy security... If it is not soon connected to generate electricity, it will both waste and cause damage to both investors and the economy, and society... I think relevant agencies will quickly sit down and remove wind power enterprises; At the same time, it is necessary to determine the responsibility of the individuals and units involved for the delay in this matter, leading to the terrible waste as mentioned above”.
“The delay, slowness in management leads to terrible damage. For businesses to invest and then don't know how to consume in the middle, so leave it there. Who will be responsible for this terrible waste? Before finding out the exact "address" responsible, the damage to the business is indisputable. The Ministry of Industry and Trade needs to quickly remove it for businesses", BD Buu An impatiently. And BD Ph. Cong wrote: "Cannot accept the bureaucratic management, need to investigate to the end the responsibility of the individuals and units involved. Must quickly and urgently implement price approval. It may not be reasonable right away, it will be adjusted later. It can't be wasted like that."